Work 1
Completed100%Physical progress
97.4%Financial progress
Scheduled start26-12-2019
Scheduled completion15-10-2024
- Contractor
- Infab Infrastructure Pvt. Ltd.
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹10,81,80,750₹10.82 crore
- Amount paid
- ₹10,54,08,760₹10.54 crore
- Paid to contractor
- ₹9,87,94,196₹9.88 crore
- Administrative sanction (AS)
- ₹12,80,00,000₹12.8 crore
- Financial sanction (FS)
- ₹12,06,54,850₹12.07 crore
- Technical sanction (TS)
- ₹10,96,61,475₹10.97 crore
- Tender amount
- ₹9,79,65,436₹9.8 crore
- Letter of acceptance (LOA)
- ₹9,79,65,436₹9.8 crore
- Current progress
- Four piers completed Right & Left side Abutments completed Right side retaining wall u/s 110/110m & d/s 50/50m completed. Left side retaining wall total U/S-87/110 L/S-D/S- 53/53m retaining wall completed. Current Financial Progress :72.53%