Regulator with Lock at Puthenkavu
In progress80%Physical progress
60.2%Financial progress
Scheduled start14-01-2021
Scheduled completion24-12-2025
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹27,27,46,788₹27.27 crore
- Amount paid
- ₹16,42,99,391₹16.43 crore
- Paid to contractor
- ₹15,38,56,632₹15.39 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹25,75,80,808₹25.76 crore
- Technical sanction (TS)
- ₹25,75,80,000₹25.76 crore
- Tender amount
- ₹27,28,43,730₹27.28 crore
- Letter of acceptance (LOA)
- ₹24,36,10,473₹24.36 crore
- Current progress
- Construction of 72 piles completed Current Financial Progress : 20% Achieved progress as on 15-06-2022 - 25.5%