WRD022-10-01 Thripunithura

Construction of Regulator cum Bridge

Total of works

₹25.76 crore

₹25,75,80,808

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Regulator with Lock at Puthenkavu

Scheduled completion was 24-12-2025. That was 282 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 1 · Since 30-09-2026

Works (1)

Regulator with Lock at Puthenkavu

In progress
80%Physical progress
60.2%Financial progress
Scheduled start14-01-2021
Scheduled completion24-12-2025
Implementing agency (SPV)
KIIDC
Contract amount
₹27,27,46,788₹27.27 crore
Amount paid
₹16,42,99,391₹16.43 crore
Paid to contractor
₹15,38,56,632₹15.39 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹25,75,80,808₹25.76 crore
Technical sanction (TS)
₹25,75,80,000₹25.76 crore
Tender amount
₹27,28,43,730₹27.28 crore
Letter of acceptance (LOA)
₹24,36,10,473₹24.36 crore
Current progress
Construction of 72 piles completed Current Financial Progress : 20% Achieved progress as on 15-06-2022 - 25.5%

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹25,75,80,808₹25.76 crore

Details

Project code
WRD022-10-01
Department
Water Resources
Constituency
Thripunithura

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org