Regulator with Lock at Parapram
Completed100%Physical progress
98.6%Financial progress
Scheduled start16-11-2020
Scheduled completion15-12-2023
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹55,84,92,913₹55.85 crore
- Amount paid
- ₹55,04,18,218₹55.04 crore
- Paid to contractor
- ₹51,54,76,773₹51.55 crore
- Administrative sanction (AS)
- ₹50,00,00,000₹50 crore
- Financial sanction (FS)
- ₹56,42,12,339₹56.42 crore
- Technical sanction (TS)
- ₹56,60,91,480₹56.61 crore
- Tender amount
- ₹49,83,85,551₹49.84 crore
- Letter of acceptance (LOA)
- ₹49,83,85,551₹49.84 crore
- Current progress
- 4 spans completed including lock portion Retaining wall u/s LB 285 m completed. Retaining wall d/s LB 382m completed. Retaining wall u/s RB 40 m completed. Retaining wall d/s RB 180m completed. Current Financial Progress : 62%