Work 1
In progress73%Physical progress
35.2%Financial progress
Scheduled start27-08-2021
Scheduled completion31-10-2025
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹26,76,77,929₹26.77 crore
- Amount paid
- ₹9,42,26,838₹9.42 crore
- Paid to contractor
- ₹8,82,37,842₹8.82 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹27,74,28,958₹27.74 crore
- Technical sanction (TS)
- ₹24,50,26,131₹24.5 crore
- Tender amount
- ₹26,76,77,929₹26.77 crore
- Current progress
- .43 no of pile foundation is completed out of 48 .Piling work for P1,P2 & P3 are complete .Piling work for A1 & A2 are ongoing .Land acquisition proposal is submitted to the Executive engineer Kozhikkode