WRD022-14-01 Elathur

Construction of Regulator cum Bridge

Total of works

₹27.74 crore

₹27,74,28,958

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · #1

Scheduled completion was 31-10-2025. That was 336 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
73%Physical progress
35.2%Financial progress
Scheduled start27-08-2021
Scheduled completion31-10-2025
Implementing agency (SPV)
KIIDC
Contract amount
₹26,76,77,929₹26.77 crore
Amount paid
₹9,42,26,838₹9.42 crore
Paid to contractor
₹8,82,37,842₹8.82 crore
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹27,74,28,958₹27.74 crore
Technical sanction (TS)
₹24,50,26,131₹24.5 crore
Tender amount
₹26,76,77,929₹26.77 crore
Current progress
.43 no of pile foundation is completed out of 48 .Piling work for P1,P2 & P3 are complete .Piling work for A1 & A2 are ongoing .Land acquisition proposal is submitted to the Executive engineer Kozhikkode

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹27,74,28,958₹27.74 crore

Details

Project code
WRD022-14-01
Department
Water Resource
Constituency
Elathur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org