Kanakkuമലയാളം
WRD022-18-03 Dharmadam

Construction of Retaining Wall, Stage and development of Garden Area of Ummenchira RCB in Kannur District

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Submitted for Confirmation by KIIFB · How we group

Location

Money trail

Estimated amount
₹42,83,41,947Estimate of sub-project WRD022-18, shared by 2 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 2 packages
₹38,24,48,80889.3% of the estimated amount

Details

Project code
WRD022-18-03
Department
Water Resources
Constituency
DharmadamMLA: Shri Pinarayi Vijayan

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of RCB across Ummenchira Puzha at Chekkupalam in Pinarayi Panchayath in Kannur District”. The figures below are for that whole project, not this package alone.

Approved
₹42,83,41,947₹42.83 crore
Paid so far
₹39,93,71,32393.2% of the amount approved

This package

Work awarded
₹0paid
₹1.34 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project