Kanakkuമലയാളം
WRD022-23-01 Puthukkad

Construction of Regulator cum Bridge

Total of works

₹27.38 crore

₹27,37,58,639

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kanathodu RCB

Scheduled completion was 31-12-2025. That was 275 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kanathodu RCB

In progress
83.4%Physical progress
74.1%Financial progress
Scheduled start13-01-2022
Scheduled completion31-12-2025
Implementing agency (SPV)
KIIDC
Contract amount
₹26,73,09,958₹26.73 crore
Amount paid
₹19,81,21,456₹19.81 crore
Paid to contractor
₹18,55,28,995₹18.55 crore
Administrative sanction (AS)
₹22,00,00,000₹22 crore
Financial sanction (FS)
₹27,37,58,639₹27.38 crore
Technical sanction (TS)
₹26,72,03,000₹26.72 crore
Tender amount
₹30,96,12,508₹30.96 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹27,37,58,639₹27.38 crore

Details

Project code
WRD022-23-01
Department
Water Resources
Constituency
Puthukkad

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…