WSS to Kodassery Pariyaram and Athirappilly Panchayaths in Thrissur District - 12 MLD SCADA operated WTP, well cum Pump house,450mm DI K(9) RWPM - 4900m,450mm DI K[9) CWGM - 10230m, 2nos VT RW and 2nos Centrifugal CW pump sets, 500 KVA & 100 KVA 11 KV/433V outdoor type transformer- 1no, 2LL OHS& 2LL Clear water sump & pump house,
Spent on this package so far
₹32.65 crore
₹32,65,01,187
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹58,60,97,748Estimate of sub-project WRD025-03, shared by 2 contract packages
- Expenditure reported · this package
- ₹32,65,01,187
- Expenditure reported · all 2 packages
- ₹47,73,97,12681.5% of the estimated amount
Details
- Project code
- WRD025-03-01
- Department
- Water Resources
- Executing agency
- Kerala Water Authority (KWA)
- Constituency
- Chalakudy
- Name as KIIFB publishes it
- KIIFB - WSS to Kodassery Pariyaram and Athirappilly Panchayaths in Thrissur District - 12 MLD SCADA operated WTP, well cum Pump house,450mm DI K(9) RWPM - 4900m,450mm DI K[9) CWGM - 10230m, 2nos VT RW and 2nos Centrifugal CW pump sets, 500 KVA & 100 KVA 11 KV/433V outdoor type transformer- 1no, 2LL OHS& 2LL Clear water sump & pump house,
What KIIFB approved and paid
On KIIFB's project status page this belongs to “WSS To Kodassery, Pariyaram and Athirappilly Panchayaths in Thrissur District”. The figures below are for that whole project, not this package alone.
- Approved
- ₹58,60,97,748₹58.61 crore
- Paid so far
- ₹52,20,38,98389.1% of the amount approved
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026