This package
Work started₹5.65 crorepaid
₹37.15 croreapproved
₹2.82 crore
₹2,81,64,708
KIIFB status: Contract Process Completed · How we group
On KIIFB's project status page this belongs to “Karode Comprehensive Drinking Water Project - Phase 1”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: