Construction of Thottappally - Naluchira Bridge in Alappuzha District
Approved by KIIFB
₹60.74 crore
₹60,73,54,325
Paid so far
₹53.82 crore
₹53,81,54,063 · 88.6% of the amount approved
Works
5
₹53.82 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹1,07,63,08,126. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹53,81,54,063.