Kanakkuമലയാളം
PWD001-32-04 Ambalappuzha

Construction of Tottappally-Naluchira Bridge in Alappuzha District - Contract - Balance work

Spent on this package so far

₹44.09 crore

₹44,08,86,195

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Naluchira Bridge

Completed
100%Physical progress
96%Financial progress
Scheduled start25-06-2020
Scheduled completion09-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹48,66,66,990₹48.67 crore
Amount paid
₹46,71,32,641₹46.71 crore
Paid to contractor
₹43,29,65,298₹43.3 crore
Administrative sanction (AS)
₹38,00,00,000₹38 crore
Financial sanction (FS)
₹60,73,54,325₹60.74 crore
Technical sanction (TS)
₹48,66,66,990₹48.67 crore
Tender amount
₹34,39,66,436₹34.4 crore
Letter of acceptance (LOA)
₹34,39,66,436₹34.4 crore
Current progress
Deck slab 11/15,concrete work for the Pylon above slab in progress,PSC girder 8/21 completed.1/2 of Extradose span box girder completed. In principle approval forRE for 47.71crores on 26/02/22.Additional contingency charge of Rs.4 lakhs transferred to LA

Money trail

Estimated amount
₹60,73,54,325Estimate of sub-project PWD001-32, shared by 2 contract packages
Expenditure reported · this package
₹44,08,86,195
Expenditure reported · all 2 packages
₹44,08,86,19572.6% of the estimated amount

Details

Project code
PWD001-32-04
Department
Public Works
Constituency
Ambalappuzha
Name as KIIFB publishes it
CONSTRUCTION OF TOTTAPPALLY-NALUCHIRA BRIDGE IN ALAPPUZHA DISTRICT - Contract - Balance work

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Thottappally - Naluchira Bridge in Alappuzha District”. The figures below are for that whole project, not this package alone.

Approved
₹60,73,54,325₹60.74 crore
Paid so far
₹1,07,63,08,126₹107.63 crore

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project