Naluchira Bridge
Completed100%Physical progress
96%Financial progress
Scheduled start25-06-2020
Scheduled completion09-10-2025
- Contractor
- Kvjosephandsonsprivatelimited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹48,66,66,990₹48.67 crore
- Amount paid
- ₹46,71,32,641₹46.71 crore
- Paid to contractor
- ₹43,29,65,298₹43.3 crore
- Administrative sanction (AS)
- ₹38,00,00,000₹38 crore
- Financial sanction (FS)
- ₹60,73,54,325₹60.74 crore
- Technical sanction (TS)
- ₹48,66,66,990₹48.67 crore
- Tender amount
- ₹34,39,66,436₹34.4 crore
- Letter of acceptance (LOA)
- ₹34,39,66,436₹34.4 crore
- Current progress
- Deck slab 11/15,concrete work for the Pylon above slab in progress,PSC girder 8/21 completed.1/2 of Extradose span box girder completed. In principle approval forRE for 47.71crores on 26/02/22.Additional contingency charge of Rs.4 lakhs transferred to LA