Kanakkuമലയാളം
PWD001-32-01

Thottappally Naluchira Bridge - Contract work

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base Zero Approved · How we group

Location

Money trail

Estimated amount
₹60,73,54,325Estimate of sub-project PWD001-32, shared by 2 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 2 packages
₹44,08,86,19572.6% of the estimated amount

Details

Project code
PWD001-32-01
Department
Public Works

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Thottappally - Naluchira Bridge in Alappuzha District”. The figures below are for that whole project, not this package alone.

Approved
₹60,73,54,325₹60.74 crore
Paid so far
₹53,81,54,06388.6% of the amount approved

This package

Work awarded
₹0paid
₹1.69 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project