Who must repair it
When PWD finishes a road or a building, the contractor stays liable for a set period to repair defects at their own cost. These are the works inside that period, as PWD lists them.
Works under liability now
245
246 works on the list in all
Liability ends within 90 days
68
After that, repairs fall to the public purse.
Contractors
65
Names as PWD publishes them.
If you see a defect: If a work on this list fails inside its period, PWD can make the contractor put it right. Report it to PWD; its own list names the office responsible for each work. PWD's list
The district is that of the PWD office handling the work; some offices also look after works in neighbouring districts.
- SIDE PROTTECTION WORK-CHITHARA PANGODU ROAD CH. 3/300 LHS &RHSRoads · Roads Sub Division KottarakkaraBaby VargheseLiable from 04-10-2023 until 04-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 06-10-2023 until 06-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 06-10-2023 until 06-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 07-10-2023 until 07-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 07-10-2023 until 07-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 08-10-2023 until 08-10-2026
- Construction of drainage facilities b/w Ch:1/000 and 1/500 in Parippally - Madathara road.-SRRoads · Roads Sub Division KollamBaby VargheseLiable from 09-10-2023 until 09-10-2026
- Construction of drainage facilities b/w Ch:1/000 and 1/500 in Parippally - Madathara road.-SRRoads · Roads Sub Division KollamBaby VargheseLiable from 10-10-2023 until 10-10-2026
- Providing drain at Kunjanadikkulam Madathilkarazhma road at Ch 0/200,Ch 0/300,Ch 2/000 & Ch 4/000 -Providing drain to Kunjanadikkulam Madathilkarazhma road Ch 0/000 to 4/360 roadRoads · Roads Sub Division KarunagappallyImamudeen .SLiable from 10-10-2023 until 10-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 11-10-2023 until 11-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 16-10-2023 until 16-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 17-10-2023 until 17-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 17-10-2023 until 17-10-2026
- SIDE PROTTECTION WORK-CHITHARA PANGODU ROAD CH. 3/300 LHS &RHSRoads · Roads Sub Division KottarakkaraBaby VargheseLiable from 17-10-2023 until 17-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 18-10-2023 until 18-10-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 19-10-2023 until 19-10-2026
- Deposit work - H&FWD - Stregthening of Emergency medical care for OP at Taluk Hospital, NeendakaraBuildings · Buildings Subdivision, KarunagappallyShiby.SLiable from 21-10-2021 until 20-10-2026
- DEPOSIT-Deposit work - Strengthening of Emergency Medical Care 2017-18 - Construction of a new OP building for Taluk hospital, Neendakara.-Work-General Civil Work-1Buildings · Buildings Sub Division KarunagappallyShibi. SLiable from 21-10-2021 until 21-10-2026
- Deposit work - Strengthening of Emergency Medical Care 2017-18 - Construction of a new OP building for Taluk hospital, Neendakara.Buildings · Buildings Sub Division KarunagappallyShibi. SLiable from 21-10-2021 until 21-10-2026
- LAC ADS- 2020-21, Kottarakkara LAC, Construction of new building for Gov.L.P.S,Mavady in Kulakkada Gramma PanchayatBuildings · Buildings Sub Division KarunagappallyShibi. SLiable from 21-10-2021 until 21-10-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 24-10-2023 until 24-10-2026
- SIDE PROTTECTION WORK-CHITHARA PANGODU ROAD CH. 3/300 LHS &RHSRoads · Roads Sub Division KottarakkaraBaby VargheseLiable from 24-10-2023 until 24-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 25-10-2023 until 25-10-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 27-10-2023 until 27-10-2026
- LAC-ADS Kunnathoor Constituency 'as spill over works 2015-16'- Construction of new building for Kothapuram LPS at West Kallada GPBuildings · Buildings Sub Division KarunagappallySabu .BLiable from 27-10-2021 until 27-10-2026
- LAC-ADS-LAC-ADS Kunnathoor Constituency 'as spill over works 2015-16'- Construction of new building for Kothapuram LPS at West Kallada GP-Work-General Civil Work-1Buildings · Buildings Sub Division KarunagappallySabu .BLiable from 27-10-2021 until 27-10-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 28-10-2023 until 28-10-2026
- SIDE PROTTECTION WORK-CHITHARA PANGODU ROAD CH. 3/300 LHS &RHSRoads · Roads Sub Division KottarakkaraBaby VargheseLiable from 30-10-2023 until 30-10-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 31-10-2023 until 31-10-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 31-10-2023 until 31-10-2026
- Kunnathoor M.L.A /L.A.C-ADS 2018-19 Bhoothakuzhy-kottamkara cluster roadRoads · Roads Sub Division KarunagappallyPresident Q 1247Liable from 31-12-2022 until 31-10-2026
- SIDE PROTTECTION WORK-CHITHARA PANGODU ROAD CH. 3/300 LHS &RHSRoads · Roads Sub Division KottarakkaraBaby VargheseLiable from 31-10-2023 until 31-10-2026
- Providing drain at Kunjanadikkulam Madathilkarazhma road at Ch 0/200,Ch 0/300,Ch 2/000 & Ch 4/000 -Providing drain to Kunjanadikkulam Madathilkarazhma road Ch 0/000 to 4/360 roadRoads · Roads Sub Division KarunagappallyImamudeen .SLiable from 01-11-2023 until 01-11-2026
- Providing drain at Kunjanadikkulam Madathilkarazhma road at Ch 0/200,Ch 0/300,Ch 2/000 & Ch 4/000 -Providing drain to Kunjanadikkulam Madathilkarazhma road Ch 0/000 to 4/360 roadRoads · Roads Sub Division KarunagappallyImamudeen .SLiable from 03-11-2023 until 03-11-2026
- NH SRV Road -NH SRV Road Construction of CC Drain at Karunagappally Bus stand PortionRoads · Roads Sub Division KarunagappallyMuhammed AfsalLiable from 07-11-2023 until 07-11-2026
- Budget Work 2019-20 .Improvements by providing BM and BC to Pazhayattinkuzhi -Sangha mukku-Kaithari mukku -Palathara Varazhikam road in Kollam corparationRoads · Roads Sub Division KollamPradeeep PLiable from 08-11-2023 until 08-11-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 08-11-2023 until 08-11-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 09-11-2023 until 09-11-2026
- Non Plan 2020-21 : Providing vehicle parking and beautification and connected woks at Court Complex, Punalur-Work-General Civil Work-1Buildings · Buildings Sub Division PunalurChandramohanan Nair RLiable from 09-11-2021 until 09-11-2026
- Police Quarters, Palayam, Thiruvananthapuram- Urgent Works such as Toilets and Kitchen Maintenance, Painting, etc. of A,B,C,D & E Blocks.Buildings · Buildings Sub Division PunalurChandramohanan Nair RLiable from 09-11-2021 until 09-11-2026
- Interior Works to the Conference Hall at Mini Civil Station Kottarakkara-Interior Works to Conference Hall-Composite WorkBuildings · Buildings Sub Division KottarakkaraSivaprasad .NLiable from 12-11-2023 until 12-11-2026
- Sabarimala Festival works 2020-21. Improvements to kulamada pallikkal road by providing DBM and BCRoads · Roads Sub Division KollamA ManafLiable from 14-11-2023 until 14-11-2026
- Budget Work 2019-20 .Improvements by providing BM and BC to Pazhayattinkuzhi -Sangha mukku-Kaithari mukku -Palathara Varazhikam road in Kollam corparationRoads · Roads Sub Division KollamPradeeep PLiable from 15-11-2023 until 15-11-2026
- NH SRV Road -NH SRV Road Construction of CC Drain at Karunagappally Bus stand PortionRoads · Roads Sub Division KarunagappallyMuhammed AfsalLiable from 15-11-2023 until 15-11-2026
- Providing drain at Kunjanadikkulam Madathilkarazhma road at Ch 0/200,Ch 0/300,Ch 2/000 & Ch 4/000 -Providing drain to Kunjanadikkulam Madathilkarazhma road Ch 0/000 to 4/360 roadRoads · Roads Sub Division KarunagappallyImamudeen .SLiable from 15-11-2023 until 15-11-2026
- BUDGET WORKS 2019-20 IMPROVEMENTS TO OYOOR AMPALAKUNNU KAITHAYIL VAPPALA ROADRoads · Roads Sub Division KottarakkaraM Abdul KhalamLiable from 16-11-2023 until 16-11-2026
- Budget Work 2019-20 .Improvements by providing BM and BC to Pazhayattinkuzhi -Sangha mukku-Kaithari mukku -Palathara Varazhikam road in Kollam corparationRoads · Roads Sub Division KollamPradeeep PLiable from 16-11-2023 until 16-11-2026
- Providing drain at Kunjanadikkulam Madathilkarazhma road at Ch 0/200,Ch 0/300,Ch 2/000 & Ch 4/000 -Providing drain to Kunjanadikkulam Madathilkarazhma road Ch 0/000 to 4/360 roadRoads · Roads Sub Division KarunagappallyImamudeen .SLiable from 18-11-2023 until 18-11-2026
- Sabarimala Festival works 2020-21. Improvements to kulamada pallikkal road by providing DBM and BCRoads · Roads Sub Division KollamA ManafLiable from 18-11-2023 until 18-11-2026
- Budget Work 2020-2021 : Providing BM & BC to Yeroor - Edamon PWD road ( Aylara Jn to Aayiranellore ) .Roads · Roads Sub Division PunalurP P Ajithkumar M D Akshaya BuildersLiable from 20-11-2023 until 20-11-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 22-11-2023 until 22-11-2026
- Construction of Compound Wall and Special Repairs to old Building of Women's Polytechnic ,Kayamkulam .Buildings · Buildings Sub Division KottarakkaraManilal TLiable from 22-11-2021 until 22-11-2026
- LAC ADS- 2020-21, Kottarakkara LAC, Construction of new building for Gov.L.P.S,Mavady in Kulakkada Gramma PanchayatBuildings · Buildings Sub Division KottarakkaraManilal TLiable from 22-11-2021 until 22-11-2026
- Sabarimala Festival works 2020-21. Improvements to kulamada pallikkal road by providing DBM and BCRoads · Roads Sub Division KollamA ManafLiable from 23-11-2023 until 23-11-2026
- GPTC Kottayam: Providing watchmen cabin,Gate and Compound wall for Mens Hostel and compound wall for Ladies Hostel.Buildings · Buildings Sub Division KottarakkaraManilal TLiable from 27-11-2021 until 27-11-2026
- General Education Department-Annual Plan 2019-20-Construction of School building of Government L.P.School,Vadakkummuri (Nannamukku G.P.) in Malappuram DistrictBuildings · Buildings Sub Division KottarakkaraManilal TLiable from 27-11-2021 until 27-11-2026
- LAC ADS ( 2020-2021),Kottarakkara-Construction of new building for Govt.W.L.PS Puthoor mukku, Kulakkada,in Kulakkada Grama PanchayatBuildings · Buildings Sub Division KottarakkaraManilal TLiable from 27-11-2021 until 27-11-2026
- LAC-ADS (2020-2021), KOTTARAKKARA LAC, Construction of new building for Govt.L.P.S Kalapila, in Veliyam Grama PanchayatBuildings · Buildings Sub Division KottarakkaraManilal TLiable from 27-11-2021 until 27-11-2026
- BUDGETWORK-2020-21 IMPROVEMENTS TO GANAPATHYNADA ARKANNOOR MANIYANMUKKU ROAD CH. 0/000 TO 4/000 KM BY PROVIDING BM&BC AND ALLIED WORKS IN CHADAYAMANGALAM LACRoads · Roads Sub Division KottarakkaraKishor. ALiable from 28-11-2023 until 28-11-2026
- Budget Work 2019-20 .Improvements by providing BM and BC to Pazhayattinkuzhi -Sangha mukku-Kaithari mukku -Palathara Varazhikam road in Kollam corparationRoads · Roads Sub Division KollamPradeeep PLiable from 07-12-2023 until 07-12-2026
Contractors with the most works
Counted by works now under liability. We treat different spellings of a name as one; two people with the same name may have been counted together.
Source
Source: the Kerala Public Works Department's DLP work list, which we read once a week. We do not keep or show the phone numbers printed on PWD's pages. The agreed amount sits in the code of PWD's page without being displayed there, so it may be provisional or out of date; PWD has filled it in for only 1 of the 245 works now under liability.