FSH002-10-12 Azhikode

GFLPS Azhikode, Kannur-Maintenance Works

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Tender Completed · How we group

Location

Money trail

Estimated amount
₹6,26,79,660Estimate of sub-project FSH002-10, shared by 13 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 13 packages
₹4,83,69,23577.2% of the estimated amount

Details

Project code
FSH002-10-12
Department
Fisheries
Constituency
AzhikodeMLA: Shri K.V. Sumesh

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Educational Infrastructure Works at Kannur District Phase-2”. The figures below are for that whole project, not this package alone.

Approved
₹6,26,79,660₹6.27 crore
Paid so far
₹5,13,47,22881.9% of the amount approved

This package

Work started
₹0paid
₹10 lakhapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…