Peruman bridge
In progress77.9%Physical progress
61.7%Financial progress
Scheduled start30-10-2020
Scheduled completion30-09-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹47,99,34,593₹47.99 crore
- Amount paid
- ₹29,58,90,652₹29.59 crore
- Paid to contractor
- ₹27,64,89,796₹27.65 crore
- Administrative sanction (AS)
- ₹60,00,00,000₹60 crore
- Financial sanction (FS)
- ₹52,37,13,082₹52.37 crore
- Technical sanction (TS)
- ₹49,20,10,272₹49.2 crore
- Tender amount
- ₹47,63,23,456₹47.63 crore
- Current progress
- All 80 out of 80 piles are completed. Also 12 out of 16 nos of pile cap, 8 out of 10 sets of piers and 8 out of 10 pier caps completed, Pier wall (Abutment) 1 out of 1,girder casting completed in perumon side and slab work in progress except centre sp