Total of works

₹52.37 crore

₹52,37,13,082

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Peruman bridge

Scheduled completion was 30-09-2025. That was 367 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Peruman bridge

In progress
77.9%Physical progress
61.7%Financial progress
Scheduled start30-10-2020
Scheduled completion30-09-2025
Implementing agency (SPV)
KRFB
Contract amount
₹47,99,34,593₹47.99 crore
Amount paid
₹29,58,90,652₹29.59 crore
Paid to contractor
₹27,64,89,796₹27.65 crore
Administrative sanction (AS)
₹60,00,00,000₹60 crore
Financial sanction (FS)
₹52,37,13,082₹52.37 crore
Technical sanction (TS)
₹49,20,10,272₹49.2 crore
Tender amount
₹47,63,23,456₹47.63 crore
Current progress
All 80 out of 80 piles are completed. Also 12 out of 16 nos of pile cap, 8 out of 10 sets of piers and 8 out of 10 pier caps completed, Pier wall (Abutment) 1 out of 1,girder casting completed in perumon side and slab work in progress except centre sp

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹52,37,13,082₹52.37 crore

Details

Project code
PWD001-38-01
Department
Public Works
Constituency
Kunnathur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026