Mattanur - Irikkur Road
Terminated92%Physical progress
98.9%Financial progress
Scheduled start09-07-2018
Scheduled completion01-08-2025
- Contractor
- M/s Irikkur Construction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹12,76,65,565₹12.77 crore
- Amount paid
- ₹12,62,31,775₹12.62 crore
- Paid to contractor
- ₹11,69,31,028₹11.69 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹45,61,91,337₹45.62 crore
- Technical sanction (TS)
- ₹12,78,00,503₹12.78 crore
- Tender amount
- ₹19,23,80,053₹19.24 crore
- Letter of acceptance (LOA)
- ₹19,23,80,053₹19.24 crore
- Current progress
- 60%.From km 0/000 to 0/300 Taring completed -as per the direction from KIIFB. MSS laying completed from 0/300 to 3/900 due to the non availability of land - DBM laying completed from 3/900 to 8/350 except the river damaged portion from Ch:5/800 to 6/400