Mattanur - Irikkur Road
In progress98%Physical progress
90.5%Financial progress
Scheduled start25-03-2023
Scheduled completion31-10-2025
- Contractor
- KMuhammed Haji
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹27,20,87,003₹27.21 crore
- Amount paid
- ₹24,63,07,959₹24.63 crore
- Paid to contractor
- ₹23,27,40,112₹23.27 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹45,61,91,337₹45.62 crore
- Technical sanction (TS)
- ₹27,20,87,004₹27.21 crore
- Tender amount
- ₹18,91,89,869₹18.92 crore
- Current progress
- 60%.From km 0/000 to 0/300 Taring completed -as per the direction from KIIFB. MSS laying completed from 0/300 to 3/900 due to the non availability of land - DBM laying completed from 3/900 to 8/350 except the river damaged portion from Ch:5/800 to 6/400