Kanakkuമലയാളം
PWD004-141-04 Ollur

2016-17 Peechi - Vazhani Tourism Corridor, Improvements with BM & BC to road from Mudikkode to Karumathra Via Chirakkekode, Ponganengad, Thanikkudam, Kundukkad ( Phase I) km 7/000 to 18/650 in Thrissur District

Spent on this package so far

₹55.19 crore

₹55,18,56,576

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Mudikkode - Karumathra Road

Scheduled completion was 31-12-2025. That was 275 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Mudikkode - Karumathra Road

In progress
78.3%Physical progress
82.6%Financial progress
Scheduled start29-07-2023
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹60,33,04,536₹60.33 crore
Amount paid
₹49,85,14,548₹49.85 crore
Paid to contractor
₹46,68,29,225₹46.68 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹88,65,09,302₹88.65 crore
Technical sanction (TS)
₹58,80,00,000₹58.8 crore
Tender amount
₹60,33,04,536₹60.33 crore
Current progress
?Once tendered and Contract with M/s EKK Infrastructure has been terminated, due to the non avalability of 10m ROW in tendered stretch of road.

Money trail

Estimated amount
₹88,65,09,302Estimate of sub-project PWD004-141, shared by 3 contract packages
Expenditure reported · this package
₹55,18,56,576
Expenditure reported · all 3 packages
₹62,86,87,67570.9% of the estimated amount

Details

Project code
PWD004-141-04
Department
Public Works
Constituency
OllurMLA: Shri K. Rajan
Name as KIIFB publishes it
KIIFB 2016-17 Peechi - Vazhani Tourism Corridor, Improvements with BM & BC to road from Mudikkode to Karumathra Via Chirakkekode, Ponganengad, Thanikkudam, Kundukkad ( Phase I) km 7/000 to 18/650 in Thrissur District

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Peechi - Vazhani Tourism Corridor, Improvements with BM & BC to road from Mudikkode to Karumathra Via Chirakkekode, Ponganengad, Thanikkudam, Kundukkad km 0/000 to 18/650 in Thrissur District”. The figures below are for that whole project, not this package alone.

Approved
₹88,65,09,302₹88.65 crore
Paid so far
₹1,52,79,66,558₹152.8 crore

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project