Mudikkode - Karumathra Road
In progress- Contractor
- M/s EKKInfrastructure Limited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,87,13,184₹19.87 crore
- Amount paid
- ₹1,26,84,029₹1.27 crore
- Paid to contractor
- ₹1,18,77,834₹1.19 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹88,65,09,302₹88.65 crore
- Technical sanction (TS)
- ₹24,91,71,789₹24.92 crore
- Tender amount
- ₹19,87,13,184₹19.87 crore
- Current progress
- ?Once tendered and Contract with M/s EKK Infrastructure has been terminated, due to the non avalability of 10m ROW in tendered stretch of road.