Kallikkadu to Parassala- second phase
Foreclosed100%Physical progress
88.8%Financial progress
Scheduled start20-02-2020
Scheduled completion31-03-2025
- Contractor
- Thajudeen A
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹34,72,27,741₹34.72 crore
- Amount paid
- ₹30,82,38,218₹30.82 crore
- Paid to contractor
- ₹29,05,26,369₹29.05 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,33,79,82,818₹133.8 crore
- Technical sanction (TS)
- ₹34,72,27,741₹34.72 crore
- Tender amount
- ₹34,25,81,051₹34.26 crore
- Letter of acceptance (LOA)
- ₹34,25,81,051₹34.26 crore
- Current progress
- Work progress - 87% . DBM - 6km completed. Eviction to be done. The proposal for RR package for 42 families submitted to Govt. through KIIFB .