Kallikkadu to Parassala
Completed100%Physical progress
94.3%Financial progress
Scheduled start26-02-2021
Scheduled completion31-07-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹51,26,65,857₹51.27 crore
- Amount paid
- ₹48,34,59,865₹48.35 crore
- Paid to contractor
- ₹45,18,84,410₹45.19 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,33,79,82,818₹133.8 crore
- Technical sanction (TS)
- ₹61,58,08,902₹61.58 crore
- Tender amount
- ₹52,47,99,547₹52.48 crore
- Current progress
- Work progress 79% . Drain - 90% DBM - completed. BC not started due to non shifting of KWA pipeline. Extension of TOC applied upto 26.11.2022 KSEB utility shifting completed. KWA utility shifting tendered.