Tanur- Mohyiudhin Palli Road-CH
Completed100%Physical progress
97.5%Financial progress
Scheduled start27-02-2021
Scheduled completion31-12-2023
- Contractor
- M/s . Malabar Tech
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹20,90,58,475₹20.91 crore
- Amount paid
- ₹20,37,58,446₹20.38 crore
- Paid to contractor
- ₹19,03,35,030₹19.03 crore
- Administrative sanction (AS)
- ₹65,00,00,00,000₹6,500 crore
- Financial sanction (FS)
- ₹27,57,00,000₹27.57 crore
- Technical sanction (TS)
- ₹27,56,00,000₹27.56 crore
- Tender amount
- ₹20,90,58,475₹20.91 crore
- Letter of acceptance (LOA)
- ₹18,66,59,352₹18.67 crore
- Current progress
- Work awarded to M/s Malabartech on 15.02.2021 and 38% completed. TOC up to 26.08.2022. Provision of 3.26 Crore for LA is included in the TS estimate. Revenue AS obtained for LA