Construction of coastal Highway in Malappuram District - Reach III: Between Tanur Mohyudhin Palli & Kettungal (Km 23/190 to 27/040)
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Project Created · How we group
Money trail
- Estimated amount
- ₹27,57,00,000Estimate of sub-project PWD014-12, shared by 3 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 3 packages
- ₹19,48,09,49870.7% of the estimated amount
Details
- Project code
- PWD014-12-03
- Department
- Public Works
- Executing agency
- Kerala Road Fund Board (KRFB)
- Constituency
- TanurMLA: Shri V. Abdurahiman
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Construction of coastal Highway in Malappuram District - Reach III: Between Tanur Mohyudhin Palli & Kettungal (Km 23/190 to 27/040)”. The figures below are for that whole project, not this package alone.
- Approved
- ₹27,57,00,000₹27.57 crore
- Paid so far
- ₹23,34,89,46284.7% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Construction of coastal Highway in Malappuram District-Reach III: Between Tanur Mohyudhin Palli & Kettungal(Km 23/190 to 27/040 - Work Contract ₹19.48 crore spent
- Construction of coastal Highway in Malappuram District - Reach III: Between Tanur Mohyudhin Palli & Kettungal (Km 23/190 to 27/040) Not published