Pazhakutty Mangalapuram road
In progress59%Physical progress
69.2%Financial progress
Scheduled start31-12-2024
Scheduled completion30-06-2026
- Contractor
- M/ssreedhanyaconstructioncompany
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹47,16,15,149₹47.16 crore
- Amount paid
- ₹32,62,48,981₹32.62 crore
- Paid to contractor
- ₹30,55,12,810₹30.55 crore
- Administrative sanction (AS)
- ₹2,00,00,00,000₹200 crore
- Financial sanction (FS)
- ₹1,69,95,69,425₹169.96 crore
- Technical sanction (TS)
- ₹37,59,55,171₹37.6 crore
- Tender amount
- ₹47,16,15,149₹47.16 crore
- Current progress
- RReach I work 34% progress. Drain - 6200/13520 m placed, 10050/13520 m casted Retaining wall - 88% done, Culvert - 14/15 completed, 1 ongoing GSB - 4.1 km, WMM - 4.05km, DBM-1.64 km + 0.908 km(Vembayam side) Bridge - pile completed (8 Nos.), pile cap 2