Pazhakutty Mangalapuram road
In progress93.2%Physical progress
18.2%Financial progress
Scheduled start23-03-2025
Scheduled completion22-01-2026
- Contractor
- Thoppilinfrastructurepvtltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,76,34,206₹13.76 crore
- Amount paid
- ₹2,50,16,284₹2.5 crore
- Paid to contractor
- ₹2,34,26,260₹2.34 crore
- Administrative sanction (AS)
- ₹2,00,00,00,000₹200 crore
- Financial sanction (FS)
- ₹1,69,95,69,425₹169.96 crore
- Technical sanction (TS)
- ₹12,93,00,000₹12.93 crore
- Tender amount
- ₹13,76,34,206₹13.76 crore
- Current progress
- RReach I work 34% progress. Drain - 6200/13520 m placed, 10050/13520 m casted Retaining wall - 88% done, Culvert - 14/15 completed, 1 ongoing GSB - 4.1 km, WMM - 4.05km, DBM-1.64 km + 0.908 km(Vembayam side) Bridge - pile completed (8 Nos.), pile cap 2