Total of works

₹123.37 crore

₹1,23,36,61,994

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Ayoor Anchal Punalur Road

Completed
100%Physical progress
87.5%Financial progress
Scheduled start30-10-2020
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹1,07,36,39,972₹107.36 crore
Amount paid
₹93,91,82,718₹93.92 crore
Paid to contractor
₹83,65,83,026₹83.66 crore
Administrative sanction (AS)
₹35,00,00,000₹35 crore
Financial sanction (FS)
₹1,23,36,61,994₹123.37 crore
Technical sanction (TS)
₹1,05,44,49,258₹105.44 crore
Tender amount
₹87,86,18,842₹87.86 crore
Letter of acceptance (LOA)
₹87,86,18,842₹87.86 crore
Current progress
Culvert construction, construction of DR walls ,Gabion walls and CC walls,Drain casting and laying, and laying of GSB and WMM in Ayur Anchal road and subgrade formation with lime stabilization, GSB and WMM laying works in Anchal bypass is in progress. B

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,23,36,61,994₹123.37 crore

Details

Project code
PWD015-19-01
Department
Public Works
Constituency
Punalur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026