Ayoor Anchal Punalur Road
Completed100%Physical progress
87.5%Financial progress
Scheduled start30-10-2020
Scheduled completion31-12-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,07,36,39,972₹107.36 crore
- Amount paid
- ₹93,91,82,718₹93.92 crore
- Paid to contractor
- ₹83,65,83,026₹83.66 crore
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹1,23,36,61,994₹123.37 crore
- Technical sanction (TS)
- ₹1,05,44,49,258₹105.44 crore
- Tender amount
- ₹87,86,18,842₹87.86 crore
- Letter of acceptance (LOA)
- ₹87,86,18,842₹87.86 crore
- Current progress
- Culvert construction, construction of DR walls ,Gabion walls and CC walls,Drain casting and laying, and laying of GSB and WMM in Ayur Anchal road and subgrade formation with lime stabilization, GSB and WMM laying works in Anchal bypass is in progress. B