Amaravila KarakkonamShooravakkanai Road
In progress30%Physical progress
33.5%Financial progress
Scheduled start25-06-2024
Scheduled completion24-06-2025
- Contractor
- Vishwa Samudra Engineering Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹31,53,63,684₹31.54 crore
- Amount paid
- ₹10,57,61,121₹10.58 crore
- Paid to contractor
- ₹9,06,99,372₹9.07 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹90,92,98,677₹90.93 crore
- Technical sanction (TS)
- ₹25,55,88,494₹25.56 crore
- Tender amount
- ₹31,53,63,684₹31.54 crore
- Current progress
- 1st Reach - TS estimate submitted. 2nd reach - FDR work tender approval in processing. Revised alignment issued. Requested Tahsildar to demarcate the purambok land.