Amaravila KarakkonamShooravakkanai Road
In progress82%Physical progress
58.5%Financial progress
Scheduled start20-11-2023
Scheduled completion19-11-2025
- Contractor
- Thajudeen A
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹39,66,54,061₹39.67 crore
- Amount paid
- ₹23,21,09,464₹23.21 crore
- Paid to contractor
- ₹21,93,23,730₹21.93 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹90,92,98,677₹90.93 crore
- Technical sanction (TS)
- ₹38,45,88,000₹38.46 crore
- Tender amount
- ₹39,66,54,061₹39.67 crore
- Current progress
- 1st Reach - TS estimate submitted. 2nd reach - FDR work tender approval in processing. Revised alignment issued. Requested Tahsildar to demarcate the purambok land.