Manassery-Pulparamba-Chullikkaparamba
Completed100%Physical progress
77.1%Financial progress
Scheduled start18-10-2021
Scheduled completion13-05-2025
- Contractor
- KKBuilders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹25,11,49,787₹25.11 crore
- Amount paid
- ₹19,36,67,580₹19.37 crore
- Paid to contractor
- ₹18,12,28,894₹18.12 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹36,79,53,794₹36.8 crore
- Technical sanction (TS)
- ₹28,35,70,000₹28.36 crore
- Tender amount
- ₹25,11,49,787₹25.11 crore
- Current progress
- Culvert work , retaining wall , drainage ,Sub grade formation and GSB laying progressing at various locations. Tree cutting also progressing