2017-2018-Improvements to Manassery-Pulparamba-Kodiyathoor-Chullikkaparamba in Kozhikode District - Phase II Improvements to Theyyathumkdavu to Kodiyathoor Village office Junction (3/980 to 4/555)
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Tender Completed · How we group
Money trail
- Estimated amount
- ₹36,79,53,794Estimate of sub-project PWD015-57, shared by 2 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 2 packages
- ₹18,53,75,10650.4% of the estimated amount
Details
- Project code
- PWD015-57-04
- Department
- Public Works
- Executing agency
- Kerala Road Fund Board (KRFB)
- Constituency
- ThiruvambadyMLA: Shri Linto Joseph
- Name as KIIFB publishes it
- KIIFB 2017-2018-Improvements to Manassery-Pulparamba-Kodiyathoor-Chullikkaparamba in Kozhikode District - Phase II Improvements to Theyyathumkdavu to Kodiyathoor Village office Junction (3/980 to 4/555)
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…