Malappuram

165 projects · ₹1,013.05 crore spent so far · 3 flagged

Sorted by: Flagged first
  1. Hill Highway - Widening and Providing BM & BC to Pookkottumpadam - Thampurattikkallu Munderi seed farm gate road (Reach 1 - ch 0/000 to 15/000) - Nilambur LAC in Malappuram District - ContractPublic Works · Nilambur₹57.86 crorespent so farOverdueWork plan
  2. Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000- Contract WorkPublic Works · Tanur,Tirur,Thavanur₹57.76 croreestimateOverdueWork plan
  3. Construction of Hill Highway Pookkottumpadam - Kalikavu Kerala Estate Kizhakkethala (Karuvarakundu) Chirakkal -km 47/890 to 68/900 (phase-2 Working chainage 47/890 to 60/200)Public Works · Nilambur₹40.53 crorespent so farOverdueWork plan
  4. Thrissivaperur Line Strengthening Package IIPower · Ponnani₹203.91 croreestimateWork plan
  5. Parappanangadi Fishing Harbour - Civil worksFisheries · Tirurangadi₹112.22 croreestimateWork plan
  6. Improvements and Providing DBM & BC Works on Kondotty-Edavannappara - Areacode road between km 0/000 and 20/968 ( excluding km 11/600 to 11/950) in Malappuram District - Phase 1 - ContractPublic Works · Kondotty₹103.07 croreestimateWork plan
  7. Augmentation of Infrastructure Facilities at Calicut UniversityHigher Education · Vallikunnu₹102.8 croreestimateWork plan
  8. PHASE II - WSS to Tanur Municipality In Malappuram District - Laying Clear Water Gravity Main And Distribution Network In Tanur MuncipalityWater Resources · Tanur₹78.44 croreestimateWork plan
  9. Hill Highway - Widening and Providing BM & BC to Pookottumpadam - Moolepadam bridge Road in Nilambur & Eranad LACs, Malappuram district 20.5 Km - Phase 1 - (Reach 1- Km 0/00 to Km 10/900, Pookottumpadam to Myladi bridge)Public Works · Ernad, Ernad,Nilambur, Nilambur₹42.04 crorespent so farWork plan
  10. Hill Highway 2017-2018 Pookottumpadam Kalikavu Kerala estate Kizhakkethala Karuvarakundu - Chirakkal Pulvetta Karinkanthoni Ponapara Km 60/200 to 68/900 -Contract workPublic Works · Nilambur,Wandoor₹39.58 crorespent so farWork plan
  11. Development of Taluk Hospital KondottyHealth & Family Welfare · Kondotty₹36.19 croreestimateWork plan
  12. Water Supply Scheme to Tanur Municipality and adjoining 4 Panchayaths - phase 1 PACKAGE 2Water Resources · Tanur₹34.51 crorespent so farWork plan
  13. Hill Highway - Widening and Providing BM & BC to Pookkottumpadam - Thampurattikkallu Munderi seed farm gate road (Reach 2 - Ch 24/280 - 34/375) - Nilambur LAC in Malappuram District - ContractPublic Works · Nilambur₹32.28 crorespent so farWork plan
  14. Budget -2017-18-KIIFB Project - TRAN 10:WRD 025-13 WSS to Ramanchadi - Aligarh in Malappuram district- Package 1Water Resources · Perinthalmanna₹31.88 crorespent so farWork plan
  15. Project 4-UWSS to Manjeri –Replacing old aged AC pipe with DI pipe in Manjeri MunicipalityWater Resources · Manjeri₹28.42 croreestimateWork plan
  16. Budget 2017 -18 - KIIFB Manjeri suburban Drinking water project : Improvemment and augmentation of UWSS to Manjeri Municipality Including water supply arrangements to Payyanad and Thadaparambu area in Manjeri Municipality of Malapuram District - Package - IWater Resources · Manjeri₹28.33 crorespent so farWork plan
  17. Budget 2017 -18- KIIFB - TRAN 10 - WRD 025 - 05 - WSS to Edayur Panchayath Including service level improvement of existing WSS to Irimblium Panchayath and Valancheri Municipality in Malappuram District - Package - II - Distribution SystemWater Resources · Kottakkal₹26.28 crorespent so farWork plan
  18. CWSS to Thiruvali & Adjoining Villages - Phase I & II - Thiruvali and Wandoor Part -1Water Resources · Wandoor₹22.2 croreestimateWork plan
  19. Construction of coastal Highway in Malappuram District-Reach III: Between Tanur Mohyudhin Palli & Kettungal(Km 23/190 to 27/040 - Work ContractPublic Works · Tanur₹19.48 crorespent so farWork plan
  20. Budget 2017 -18 - WSS to Ramanchadi - Aligarh in Malappuram District - Package - II - Laying Distribution MainWater Resources · Perinthalmanna₹18.98 crorespent so farWork plan
  21. Project TRANCHE - 8 - WRD -025-14 - Comprehensive Drinking Water Supply Scheme to Edavanna Panchayat in Malappuram District - Package - IWater Resources · Ernad₹16.73 crorespent so farWork plan
  22. Development of THQH Tirurangadi,Malappuram DistrictHealth & Family Welfare · Tirurangadi₹13.79 croreestimateWork plan
  23. Project:Tranche 13: WRD004-02-Improvements to WSS of Kondotty Muncipality-Phase II-Package IIA- Design, Construction & Commissioning of 14 LL Capacity OHSR at Kumbalapara, Supply, Laying, Testing and Commissioning of pumping mains and transmission mains, Design, supply, erection, testing and commissioning of CF clear water pump setsWater Resources · Kondotty₹12.92 crorespent so farWork plan
  24. Project:Tranche 13: WRD004-02-Improvements to WSS of Kondotty Muncipality-Phase II-Package II- Design, Construction & Commissioning of 6 LL, 8 LL Capacity OHSR, Supply, Laying, Testing and Commissioning of transmission mains, and Distribution to Zone 4 Melangadi AreaWater Resources · Kondotty₹12.18 crorespent so farWork plan